Ipswich Garden Suburb - Henley Gate Neighbourhood

Henley Gate - Delivery and Planning Information

Construction Work

Crest Nicholson have been constructing Phase 1 of Henley Gate since September 2021 and the development has started to be occupied by residents. Below are photos of the development taken in November 2023. 

Site photos of Phase 1 of the Henley Gate Neighbourhood taken in November 2023

Crest Nicholson have also commenced development of Phase 3a which includes the Local Centre and the core infrastructure for Phases 1b, 2, and 3. 

Barratt David Wilson Homes received approval for  Phase 2a in April 2023 and Phase 2b in August 2024. Work has commenced on both sites. Below are photos of the site taken in November 2023.

Site Photos of Phase 2 of the Henley Gate Neighbourhood taken November 2023 2023 2023

The two railway bridges associated with Ipswich Garden Suburb are under construction and are not yet available for public use. Below are photos taken in November 2023.

Photos of the two railway bridges associated with the Ipswich Garden Suburb taken November 2023

Works to create the Country Park  are ongoing. Below is a link to a video showing photos of the Country Park taken in November 2023.

Video of site photos of the Country Park taken November 2023

For further details and to subscribe to the mailing list for news and updates from the developer, please visit the Crest Nicholson website. This website also provides contact details for Crest Nicholson's Community Liaison Team.      

Community Liaison Group

As part of the approved Community Development Strategy for IP/16/00608/OUT, Crest Nicholson have established a Community Liaison Group comprising members from local stakeholder groups and the community. The purpose of this group is to share updates throughout the construction and development of Henley Gate and provide a regular forum to discuss issues arising with Henley Gate. The Community Liaison Group is to evolve over time to include the new residents of Henley Gate and the management company, with the aim of eventually being taken over by residents as the development nears completion.

Outline Planning Permission - IP/16/00608/OUT

Outline Planning Permission was granted on 31st January 2020. This permission covers the land highlighted in the image below and forms the majority of the Henley Gate Neighbourhood:

                                                        Henley Gate Neighbourhood Map

This grants Outline Permission for 1100 dwellings alongside, a new primary school, local centre comprising a mix of retail units and a new 30ha country park with a visitor centre. This development will also include 25 self build plots, a vehicular railway bridge and a pedestrian bridge. This application was determined by Planning and Development Committee in April 2018 and a Section 106 Legal Agreement was completed on 30th January 2020. A full summary of the proposed development and all the information submitted is available to view with the application on the below link. This includes the Committee Report, Officer Update Report, and Decision Notice.

Reserved Matters Applications

The following Reserved Matters Applications, pursuant to the Outline Permission detailed above, have been approved in relation to Residential Phases 1, 2 and 3 and Country Park Phases 1-7. These are listed below:

Residential Phases

Henley Gate Phase 1 street elevation to Henley RoadHenley Gate Phase 1 street elevation for east - west primary road

Image showing the approved street scene of Phase 2 along the new primary road

Image showing the approved street scene of Phase 2 along the western boundary

Image showing the approved street scene of Phase 2 along the northern boundary

Country Park

IGS- Country Park Phase 1- General Arrangement   IGS- Country Park Phase 2-6- General Arrangement

 

The approved floor plans for the IGS Country Park Visitor CentreIGS Country Park Visitor Centre Landscape Masterplan

Railway Bridges

The application for the construction of one vehicular bridge and one pedestrian and cycle bridge over the existing railway line was approved on the 8th of August 2022. 

View the application details and decision notice: IP/22/00459/FUL

View the Committee Papers and Minutes

An application to vary condition 1 of IP/22/00459/FUL was approved on 15th February 2023. This allowed for an increase in height to the pedestrian and cycle bridge. 

View the application details, Officer Report, and decision notice: IP/22/00985/VC

The two bridges form part of the Henley Gate Neighbourhood and the Fonnereau Neighbourhood of Ipswich Garden Suburb and relate to the approved outline planning permissions IP/14/00638/OUTFL and IP/16/00608/OUT. 

                                                                                                                                                     3D visualizations of the vehicular bridge over the railway line associated with IGS 3D visualizations of the pedestrian and cycle bridge over the railway line associated with IGS

The two bridges are under construction and are not yet available for public use. A temporary diversion of Public Footpath 18 is in place as approved under application IP/21/01050/CON which discharged condition 16 (Temporary Rail Crossing Diversion Strategy) of IP/16/00608/OUT.

Discharge of Conditions

The following conditions attached to the Outline Planning Permission IP/16/00608/OUT have been approved:

  • Condition 9 - Phasing Strategy - details approved on the 24th May 2024 under application IP/23/00904/CON. This condition was previously approved under application IP/20/00200/CON. The revised Phasing Strategy approved under IP/23/00904/CON alters the path in Country Park Phase 6.
  • Condition 10 - Overarching Design Code - details approved on the 15th June 2021 under application IP/20/00200/CON.
  • Condition 11 - Country Park Phase 1 Design Code approved on 15th June 2021 under application IP/20/00418/CON.
  • Condition 11 - Phase 1 Design Code approved on 29th June 2021 under application IP/20/00312/CON.
  • Condition 11 - Country Park Phase 2-6 Design Code approved on 4th January 2022 under application IP/21/01082/CON. An updated version was approved on 6th June 2024 under application  IP/22/00805/CON.
  • Condition 11 - Phase 2 Design Code approved on 27th February 2023 under application IP/22/00509/CON.
  • Condition 11- Phase 3 Design Code approved 27th March 2024 under application IP/23/00222/CON.
  • Condition 11- Earthworks for School Phase approved on 5th June 2025 under application IP/25/00204/CON.
  • Condition 12 - Site Wide Foul and Surface Water Drainage Strategy - details approved on the 4th April 2022 under application IP/21/01268/CON. This condition was previously approved under applications IP/20/00096/CON and IP/20/00782/CON. IP/21/01268/CON alters the previously approved foul water drainage to include an additional pumping station.
  • Condition 13 - Site Wide Energy Strategy- details approved on 21st May 2021 under application IP/20/00199/CON.
  • Condition 14 - Site Wide Ecology Strategy -  details approved on the 20th November 2020 under application IP/20/00140/CON.
  • Condition 14 - Site Wide Ecology Strategy -  Addendum to Overarching Ecology Strategy approved on 21st June 2024 under application IP/24/00425/CON.
  • Condition 15 - Site Wide Archaeology Strategy- details approved on 8th January 2021 under application IP/20/00200/CON.
  • Condition 16 - Temporary Rail Crossing Diversion Strategy - details approved on 10th November 2021 under application IP/21/01050/CON.
  • Condition 19 - Foul and Surface Water Drainage- Asset Register for Phase 1, part discharged on 25th May 2023 under application IP/22/00870/CON.
  • Condition 19 - Foul and Surface Water Drainage- Asset Register for Phase 2a, discharged on 10th April 2025 under application IP/22/00765/CON.
  • Condition 19 - Foul and Surface Water Drainage- Asset Register for Phase 2b, discharged on 10th April 2025 under application IP/24/00806/CON.
  • Condition 20 - Initial Construction and Environmental Management Plan- details approved on 13th September 2021 under application IP/21/000323/CON.
  • Condition 20 - Initial Construction Environmental Management Plan- southern construction access- details part approved on the 17th May 2023 under application IP/21/01128/CON.
  • Condition 20 - Full Construction Environmental Management Plan – details part approved on the 17th May 2023 under application IP/21/01124/CON.
  • Condition 21 - Phase 1 Archaeological Works- details approved on 25th February 2021 under application IP/20/00201/CON and 25th February 2022 under application IP/21/01144/CON.
  • Condition 22 - Programme of Archaeological Work and Written Scheme of Investigation - details part approved on 25th February 2022 under application IP/21/01144/CON.
  • Condition 22 - Programme of Archaeological Work and Written Scheme of Investigation - details part approved on 20th October 2022 under application IP/22/00667/CON.
  • Condition 22-  Programme of Archaeological Work and Written Scheme of Investigation- retrospective application for parts B & C for Country Park details approved in part on 25th June 2025 under application IP/24/00856/CON.
  • Condition 23 - Contamination - details approved on the 25th February 2021 under application IP/20/00201/CON.
  • Condition 24 - Southern Construction Access - details approved on the 27th August 2021 under application IP/20/00201/CON.
  • Condition 25 - Arboricultural Method Statement (Northern and Southern Construction Access)- details approved 13th May 2021 under application IP/20/00201/CON.
  • Condition 26 - Arboricultural Method Statement- Country Park Phase 1- details approved on 22nd December 2021 under application IP/21/01022/CON.
  • Condition 26 - Arboricultural Method Statement - Phase 1 Housing and Infrastructure- details approved on the 18th March 2022 under application IP/21/00810/CON.
  • Condition 26 - Arboricultural Method Statement - Phase 1 and 1b Core Infrastructure- details approved in part on the 22nd August 2022 under application IP/22/00131/CON.
  • Condition 26 -Arboricultural Method Statement – Phases 2-6 details approved in part on the 15th June 2023 under application IP/22/00664/CON.
  • Condition 26 -Arboricultural Method Statement – Phase 3b details approved in part on the 16th September 2024 under application IP/23/00756/CON.
  • Condition 26 -Arboricultural Method Statement – Phase 7 of the Country Park details approved in part on the 2nd October 2024 under application IP/24/00496/CON.
  • Condition 26 -Arboricultural Method Statement – Phase 3a details approved in part on the 10th March 2025 under application IP/24/00691/CON.
  • Condition 26 -Arboricultural Method Statement – Phase 2b details approved in part on the 9th January 2025 under application IP/24/00781/CON.
  • Condition 27 - Pedestrian, Cycle and Maintenance Access- details approved 29th October 2021 under application IP/20/00201/CON.
  • Condition 28 - Community Development Strategy- details approved 13th May 2021 under application IP/20/00943/CON.
  • Condition 28 - Community Development Strategy- Full details of pre-occupancy phase- details approved 5th August 2021 under application IP/21/00665/CON.
  • Condition 28 - Community Development Strategy- Wayfinding Strategy - details approved on 19th July 2024 under application IP/23/00223/CON.
  • Condition 29 - Northern Access- details approved 13th May 2021 under application IP/20/00201/CON.
  • Condition 31 - Southern Access - details approved on the 27th August 2021 under application IP/20/00201/CON.
  • Condition 36 - Archaeological Investigation Submission- details part approved on 25th February 2022 under application IP/21/01144/CON.
  • Condition 36- Final post investigation Archaeological Assessment for Country Park and Residential Phases 2-7) approved on 6th September 2024 under application IP/24/00451/CON.
  • Condition 37- Contamination Verification Submission (plots 87 and 88 of Phase 1)- details part approved on 22nd January 2024 under application IP/23/00877/CON.

Other applications to discharge the planning conditions to IP/16/00608/OUT are currently under consideration. These include:

  • Condition 9- Phasing Strategy
  • Condition 26- Arboricultural Method Statement for Phases 1b. 2, and 3 Core Infrastructure
  • Condition 27- Westerfield Road and Lower Road Maintenance access
  • Condition 28- Community Development Strategy- Early Occupancy Phase
  • Condition 30- Traffic Monitoring Strategy

Other parts of the Henley Gate Neighbourhood- Former Hockey Pitch, Land Opposite 289-299 Henley Road

An outline application on the Former Hockey Pitch on Henley Road was approved on the 1st May 2024 and is subject to a S106 Agreement dated 25th April 2024. This permission is for up to 28 dwellings with all matters except access reserved. The application site is located to the east of Henley Road and north of the land covered by outline planning permission IP/16/00608/OUT detailed above and being developed by Crest Nicholson and Barratt David Wilson Homes. The application site is part of the Henley Gate Neighbourhood of the Ipswich Garden Suburb Allocation under Policy CS10 of the adopted Local Plan and is included in the adopted Ipswich Garden Suburb Supplementary Planning Document. This application was considered by Planning and Development Committee on 9th February 2022. 

View the application details and decision notice: IP/20/01093/OUT

View the Committee Papers and Minutes

This page will be updated with new information to the Henley Gate Neighbourhood. Please click on the following link to view ‘current news’ on Ipswich Garden Suburb.